Design of PE Pipe and Hydrant Valve Installation

Client: Metal Maintenance

Project: Design of a PE pipe run and hydrant valve installation in a Gold Coast Water Treatment Plant (WTP) Pump Room

Date: 08/2018             Time to Completion:  3 weeks

Deliverables:

  • General arrangement drawings for pipe run enabling the installation of a hydrant valve external to a pump rump.
  • Supply of fabrication drawings for custom stainless steel ‘T-pieces’ and supports.

Description: Ferrier Engineering was engaged by Metal Maintenance to laser scan, design and draft a hydrant valve installation for a Gold Coast Water Treatment Plant. The design including fabricated stainless steel ‘T-pieces’, PE pipe, pipe support and pressure-relief valves.

Pump Room ‘Fly-through’ Showing Hydrant Valve and Tie-In Spool